1️⃣ What “Half-Hourly (HH / Profile 00)” Means
Half-Hourly (Profile Class 00) means the site settles electricity usage in 48 half-hourly periods per day.
HH is a settlement category, not a single meter model.
All HH meters:
• Record consumption every 30 minutes
• Require full HH data for pricing
• Are priced and risk-assessed differently by suppliers
However, not all HH meters are equal.
2️⃣ HH Meter Types (This Is Where Most Confusion Happens)
🔹 Whole Current (WC) HH Meters
What they are
• The meter measures current directly
• No external transformers
• Typically lower-capacity sites
Commercial reality
• Broadest supplier support
• Still subject to minimum EACs and credit rules
• Easier to price than CT meters
Typical use cases
• Smaller HH sites
• Lower kVA connections
🔹 Current Transformer (CT) HH Meters
What they are
• Use external Current Transformers (CTs) to step down high current
• Required for high-capacity supplies
• Always indicate a more complex, higher-risk site
This is critical:
CT meters are a subset of HH meters, but they are not supported by many suppliers.
Commercial reality
• Supplier support is limited
• Higher minimum EAC thresholds
• Stricter credit and underwriting
• Multi-year terms often unavailable
This is why many HH tickets end with very few options.
🔹 AMR (P2) vs Smart HH (P4)
This is a communications distinction, not a supplier acceptance one.
• AMR / P2: Older HH meters with bolt-on comms
• Smart HH / P4: Integrated smart HH meters
👉 This does not materially change supplier eligibility.
The deciding factor is almost always WC vs CT + consumption size.
3️⃣ Supplier Support Reality (Acquisitions)
⚠️ CT HH Meters — Typical Position
EDF I&C
• Minimum EAC: ~500,000 kWh
• Below this: not supported
British Gas Business (BGB)
• Minimum EAC: ~350,000 kWh
• Must also pass banding (Bands 1–4 only)
E.ON
• Not supported for CT HH acquisitions
Smartest Energy
• Not supported for CT HH acquisitions
Valda Energy
• Supported for 1-year terms only
• Subject to credit approval
• Matrix pricing only
📌 For sub-threshold CT HH sites, Valda 1-year is usually the only viable outcome.
⚠️ Whole Current HH Meters
• Wider supplier access than CT
• Still subject to EAC thresholds
• Still require full HH data and documentation
Do not assume WC = easy; it is simply less restrictive than CT.
4️⃣ HH / 00 Quote Process (Mandatory)
All HH quotes — WC or CT — follow the same process.
👉 HH quotes must be logged via a ticket.
Emails are not monitored for HH pricing.
📄 Required Documents (All Mandatory)
Attach all of the following:
1️⃣ 12 months HH consumption data (Excel format)
2️⃣ Recent bill (issued within last 3 months)
3️⃣ Valid LOA matching customer name and supply address
Missing any item will block or delay the quote.
These are supplier rules, not BOS policy.
🧮 Valda Price Lookups (Important)
When using Valda matrix pricing:
• Load the correct regional tab
• Match the LLF column only
That’s it.
❌ Do not match Profile Class
❌ Do not match MTC / SSC
These values do not affect the price for Valda HH matrix rates.
Matching the region + LLF gives the correct price.
5️⃣ BGB Banding Check (If Relevant)
Before submitting for BGB:
📁 Pricing → BGB → TCR BANDING TOOL v3.xlsx
Enter:
• PES
• LLF
Valid bands: 1–4
If it returns 0, BGB will not support that configuration.
Check banding before raising follow-up tickets.
6️⃣ Common Questions (Answered Once)
“Can BOS make an exception?”
No. Supplier underwriting rules are fixed.
“Can we try anyway?”
Submitting below thresholds results in rejection and delays.
“Why did I have to raise a ticket if the answer is no?”
HH tickets validate eligibility; they do not override supplier rules.
“Why am I being told Valda 1-year only?”
Because CT HH + sub-threshold consumption removes other options.
7️⃣ Best Practice (Read This)
• Confirm HH type first (WC vs CT)
• Check EAC against supplier minimums
• Assume Valda 1-year for small CT HH sites
• Raise one complete ticket, not multiple partial ones
🔁 Re-raising or bumping HH tickets will not change supplier acceptance.
📣 Final Word
Half-Hourly quoting is about eligibility first, pricing second.
Most HH frustration comes from misunderstanding meter type, not missing paperwork.
Check once.
Submit once.
Move on. ☕⚡